Question
Which of the following describes RFP?
Select one:
Requirements for a Project issued by the customer
Request for Project issued by vendor
Request for Proposal issued by the customer
Requirements for Proposal prepared by vendor
The correct answer is: Request for Proposal issued by the customer
Question
The following closely resembles a software contract
Select one:
Purchase Order issued by the customer
MoU between customer and vendor
Legal document containing Terms & Conditions
Requirements document prepared by customer
The correct answer is: MoU between customer and vendor
Question
The ownership of software developed in a typical project with T&M model rests with
Select one:
Vendor
Customer
Jointly shared between customer and vendor
Escrow agency
The correct answer is: Customer
Question
Limited Tendering process is normally used for
Select one:
Select projects with unique technology
Maintaining confidentiality
Eliminating competition
Identifying and eliminating weak vendors
The correct answer is: Select projects with unique technology
Question
The primary goal of agile methodology is
Select one:
Reduce documentation overhead
Produce time-to-market products/services
Develop product in close collaboration with customers
All the mentioned
The correct answer is: All the mentioned
Question
The following is one approach for Risk Transfer in projects
Select one:
Buy insurance from third-party agencies
Distribute risk equally between customer and vendor
Customer managing risk
All the mentioned
The correct answer is: Buy insurance from third-party agencies
Question
Function Point (FP) Method of estimation is best used when
Select one:
Actual size of the final code (SLOC) is not known
Requirements are unclear
Technology/Development Tools are not yet known
Water-Fall Model is adopted as development methodology
The correct answer is: Technology/Development Tools are not yet known
Question
SCRUM Meetings are conducted in one of the variations of
Select one:
Rapid Prototyping model
Agile Model
Incremental & Iterative Model
All the mentioned
The correct answer is: Agile Model
Question
The key role of Program Manager is one of
Select one:
Resource Leverage across projects
Escalation point above Project Manager
Project Information Reporting to Steering Committee
Relationship Management with customer
The correct answer is: Resource Leverage across projects
Question
The major goal of RAD model of development is
Select one:
Reduce cost of development and time
Identify erroneous requirements early in the project
Prototype development before undertaking investment
Avoid Risk Management
The correct answer is: Reduce cost of development and time
Question
Identification of regulatory standards for development is done during
Select one:
Requirements analysis
Contract preparation
Quality Planning
All the mentioned
The correct answer is: All the mentioned
Question
Requirements for Proposal is prepared by
Select one:
Vendor as self-assessment of its capabilities
Customer as part of investigating vendor potential
Third-party agency to assess credit-worthiness of customer
Customer during the closure of the project
The correct answer is: Customer as part of investigating vendor potential
Question
Assignment of People to activities in projects is done during the following phase
Select one:
Activity Planning
Resource Scheduling
Skill Assessment
Project Monitoring & Control
The correct answer is: Resource Scheduling
Question
Warranty Maintenance of product commences when
Select one:
Acceptance and Delivery of the product is completed
Integration Testing is complete
A separate Maintenance contrast is issued by the customer
Defects start surfacing in the delivered product
The correct answer is: Acceptance and Delivery of the product is completed
Question
Going by the experience of many IT projects in India, Fixed-Price Contracts are mostly advantageous to
Select one:
Customer
Vendor
Risk Manager
Finance Manager
The correct answer is: Customer
Question
The following tool can be used for Project Status Reporting
Select one:
GANTT chart
MS-Excel
MS-Project
All the mentioned
The correct answer is: All the mentioned
Question
Risk Analysis is done in Sprial Model of development after
Select one:
Every iteration
Requirements phase
System Testing
All the mentioned
The correct answer is: Every iteration
Question
Software Product Quality is primarily determined by
Select one:
No. of Defects reported
Usability
Schedule/Cost overrun
Marketability
The correct answer is: No. of Defects reported
Question
The role of Project Steering Committee is
Select one:
a. Govern day-to-day operations of the project
b. Report project status to the CEO
c. Escalation mechanism setup by the customer
d. High-level monitoring of the project by key stakeholders
The correct answer is: High-level monitoring of the project by key stakeholders
Question
Critical Path in a project activity network diagram indicates
Select one:
Chain of activities requiring common resources
Path of least resistance to delay
Activities whose resources cannot be scheduled late
Activities which have zero or minimum float
The correct answer is: Activities which have zero or minimum float
Question
Contingency measures in Risk Planning are provided for
Select one:
Preventing potential risks identified early on
Reduce the probability of occurrence of risk events
Reducing the impact of risk should it occur
Minimizing the cost of risk mitigation activities
The correct answer is: Reducing the impact of risk should it occur
Question
To shorten the duration of a project, the following can be done
Select one:
Reducing the duration of activities on critical path
Eliminating non-critical activities
Providing more resources to activities with large float
By employing critical-chain analysis
The correct answer is: Reducing the duration of activities on critical path
Question
The following method of project monitoring is more appropriate for T&M projects
Select one:
Weekly or Monthly review
Milestone based
Decision-point based
Upon acceptance criteria
The correct answer is: Weekly or Monthly review
Question
Earned Value Analysis (EVA) helps in
Select one:
Cost-monitoring of project
Monitoring of schedule overruns
Monitoring of cumulative effort overrun
All the given options are .
The correct answer is: All the given options are .
Question
COCOMO II is a software estimation tool based on
Select one:
Parametric method of cost estimation
Function-point analysis of size
Analogical reasoning of past projects
Euclidian distance between similar projects
The correct answer is: Parametric method of cost estimation
Question
As a software manager, when you will decide the number of people required for a software project?
Select one:
a. Before the scope is determined.
b. None of the given options.
c. Before an estimate of the development effort is made.
d. After an estimate of the development effort is made.
The correct answer is: After an estimate of the development effort is made.
Question
Which of the following is an important factor that can affect the accuracy and efficacy of estimates?
Select one:
a. Project complexity
b. Degree of structural uncertainty
c. Planning process
d. Project size
The correct answer is: Project size
Question
Which of the following is a collection of component versions that make up a system?
Select one:
a. Baseline
b. None of the mentioned
c. Version
d. Codeline
The correct answer is: Baseline
Question
Earned value analysis does not integrate:
Select one:
a. Quality
b. Risk Register
c. Time
d. Cost
The correct answer is: Quality
Question
Identify the sub-process of process improvement
Select one:
a. Process distribution
b. De-processification
c. Process analysis
d. Process introduction
The correct answer is: Process analysis
Question
During which stage of Risk planning are risks prioritized based on probability and impact?
Select one:
a. Identify Risks
b. Perform Qualitative risk analysis
c. Plan Risk responses
d. Perform Quantitative risk analysis
The correct answer is: Perform Qualitative risk analysis
Question
The degree to which the design specifications are followed during manufacturing is known as_______. [ ]
Select one:
a. Quality of design
b. Quality of coding
c. Quality of conformance
d. Quality of testing
The correct answer is: Quality of conformance
Question
Risk monitoring is associated with which phase of the SDLC?
Select one:
a. Project Planning
b. Project Closure
c. Project Execution
d. Project Initiation
The correct answer is: Project Execution
Question
Which of the following is not a project constraint?
Select one:
a. Scope
b. Budget
c. Team
d. Resources
The correct answer is: Team
Question
Which of the following is incorrect activity for the configuration management?
Select one:
a. System management
b. Change management
c. Internship management
d. Version management
The correct answer is: Internship management
Question
If probability of risk is 50% and the impact is 9 what is the risk priority?
Select one:
a. 4.6
b. 4.3
c. 4.4
d. 4.5
The correct answer is: 4.5
Question
Risk management is one of the most important jobs for a
Select one:
a. Project manager
b. Production team
c. Investor
d. Client
The correct answer is: Project manager
Question
Root Cause Analysis relates to:
Select one:
a. Quality Audits
b. Process Analysis
c. Performance Measurements
d. Quality Control Measurements
The correct answer is: Process Analysis
Question
Review process works best when number of members are in between:
Select one:
a. 5-7
b. 2-3
c. 5-6
d. 4-7
The correct answer is: 5-7
Question
PPP can serve its purpose, if we eliminate projects that incur excessive
Select one:
a. B: Validity
b. A: Risk
c. Both A: & C:
d. C: Cost
The correct answer is: Both A: & C:
Question
Identify artifacts you refer while writing the test cases ?
Select one:
a. C: Test case document
b. A: Functional requirement specification
c. A: & B: only
d. B: Use Cases
The correct answer is: A: & B: only
Question
Typical selection process is i. Create a job specification ii. Obtain applicants iii. Select potential candidates from CVs. iv. Other procedures. v. Further selection, including interview vi. Create a job holder profile. The order is:
Select one:
a. i, iii, v, ii, vi, iv
b. i, ii, iii, iv, v, vi
c. i, ii, vi, iii, v, iv
d. i, vi, ii, iii, v, iv
The correct answer is i, vi, ii, iii, v, iv
Question
As per Tuckman and Jensen, five basic stages of team development are Forming, Storming, Norming, Perfroming, Adjouring. The meaning of storming is
Select one:
a. The emphasis is now on the tasks in hand
b. Conflict arise as various members of the group try to exert leadership and the group’s methods of operation are being established
c. The members of the group get to know each other
d. Conflicts are largely settled and feeling of group identity emerges
The correct answer is: Conflict arise as various members of the group try to exert leadership and the group’s methods of operation are being established
Question
You are managing a project with budget at completion (BAC) $ 80,000. The actual cost to date you have seen is $ 25,000 and earned value is $ 17,000. You calculate estimate to complete (ETC) to $ 75,000 by doing bottom-up sum of all costs. After so many calculations, what is the estimate at completion (EAC) for the project?
Select one:
a. $ 60,000
b. $ 100,000
c. $ 53,000
d. $ 57,000
The correct answer is: $ 100,000
Question
What are the 2 important factors associated with Risk?
Select one:
a. Issue & Effect
b. Cause & Effect
c. Cause & Issue
d. Effect & Probability
The correct answer is: Cause & Effect
Question
When do you think Quality Assurance/planning activities should start?
Select one:
a. should start from the beginning of the project. Correct
b. should start at the end of implementation of the project.
c. should start after the development phase of the project.
d. should start after the solutioning phase of the project.
The correct answer is: should start from the beginning of the project.
Question
Which of the following is not a project factor that should be considered when planning the structure of software engineering teams?
Select one:
a. The difficulty of the problem to be solved
b. High frustration caused by personal, business, or technological factors that causes friction among team members
c. The rigidity of the delivery date
d. The degree of sociability required for the project
The correct answer is: The degree of sociability required for the project
Question
A highly cohesive team needs to guard against the problem of
Select one:
a. Social loafing
b. Bureaucratic bypass syndrome Incorrect
c. Groupthink
d. over communication
The correct answer is: Groupthink
Question
Question